Entergy Warehouse
BEAUMONT, TX
Five-S began work with a densely wooded jobsite and performed:
Clearing, mulching, and haul-off of all vegetation on 25+ acres.
Stripped the site of unsuitable material.
Digging of retention pond.
Hauling in and placement of 25,000 CY of select fill material for the transmission warehouse building
Cut 800 tons of lime underneath the paving and roads.
Awarded additional phases of site development following phase I.